Case introduction
Shipai Road, Taipei City (near MRT Shipai Station)
• Update method: The implementer adopts the right transformation method
• Base area: about 920 ping
• Floor plan: B5/14F, 33F
• Approved quota: about 2.1 billion yuan
• Highlights of this case: The reconstruction plan is a residential and commercial building, and the bank seeks construction financing, land financing, working capital, green building deposit and other quotas. (under construction)